Southey Pipeline July 2010Click on photos to get larger images Rights to Photos |
 |
 |
 |
|
|
|
 |
 |
 |
|
|
|
 |
 |
 |
|
|
|
 |
 |
 |
|
|
|
 |
 |
 |
|
|
Taking a pump to the right place |
 |
 |
 |
|
Positioning the pump |
|
 |
 |
 |
|
|
|
 |
 |
 |
|
|
New Culvert under Markinch Grid |
 |
 |
 |
| What's all the activity? |
Approaching Loon Creek |
Road Closed |
 |
 |
 |
| Going under Highhway #6 |
|
Link to related site |
 |
| 15 km. of 8 in pipe.:: 9 pumps:: 6-7 days of pumping.:: Lower level of evaporating pond by 2-3 ft.:: Cost:$300,000. |
 |
 |
 |
| Pumping started: July 29 |
|
|
 |
 |
 |
|
|
Intake |
 |
 |
 |
| Level... |
At Beginning of Pumping |
Unidentified Tracks |
 |
 |
 |
|
Outlet at.. |
Loon Creek |
 |
 |
 |
| 1600 gal/min |
Upstream Loon Creek |
Monitoring the Pump |
 |
 |
| . |
| . |  |
|---|
|
| After Pumping |
Compare with Previous Level |
Building up the Berme |
 |
|
Pumping has stopped; August 5th |
|